Update dated 12 August 2026: Supreme Court of India, The Assistant Commissioner ST & Ors. v. M/s Siemens Gamesa Renewable Power Private Limited, SLP (Civil) Diary No. 31257/2026, order dated 12 August 2026. The Supreme Court condoned the delay but dismissed the Revenue's SLPs against the Andhra Pradesh High Court's common order dated 3 December 2025, which held that Wind Turbine Generators (WTGs) are movable goods, so their supply and erection is a composite supply taxable at 5% and not an 18% works contract.
🗣️ Saral bhasha mein samjhein
- Siemens Gamesa ne 2017-18 aur 2018-19 mein WTG supply + erection contracts par 5% GST bhara tha, composite supply maan kar.
- Department ne kaha ki WTG zameen se jude hain, isliye yeh immovable property par works contract hai aur 18% lagega. Assessment (30.12.2020), appeal (29.10.2021) aur penalty orders bhi banaye gaye.
- AP High Court ne Bharti Airtel (SC) ke 6 tests lagaye: tower parts mein aata hai, site par assemble hota hai, aur bina damage dismantle karke dusri jagah lag sakta hai. Sirf foundation fixed hai.
- Result: WTG = movable goods, contract = composite supply, works contract nahi. Tax aur penalty orders set aside, matter fresh assessment ke liye remand.
- Supreme Court ne 12.08.2026 ko Revenue ki SLP dismiss kar di, toh yeh view ab final hai.
📲 Sawal hai? WhatsApp karein: 8051331315
Facts
Siemens Gamesa manufactures, supplies and erects Wind Turbine Generators. During 2017-18 and 2018-19 it executed contracts for the manufacture and erection of WTGs for customers and paid GST at 5%, treating each contract as a composite supply of goods and services. The Assistant Commissioner (ST), Kavali Circle, Nellore, treated the contracts as works contracts relating to immovable property taxable at 18% and passed two assessment orders dated 30 December 2020 (July 2017 to March 2018, and April 2018 onwards, with disputed turnover up to March 2019). The appellate authority confirmed them on 29 October 2021. Penalty orders followed and were confirmed in appeal on 10 April 2024. Four writ petitions followed before the Andhra Pradesh High Court.
Issue
Is a Wind Turbine Generator erected on a concrete foundation movable or immovable property, and therefore is its supply and erection a composite supply under Section 2(30) of the CGST Act or a works contract under Section 2(119)?
Arguments
The Revenue argued that a WTG cannot generate power unless it is permanently attached to a platform embedded in the earth, that the unit must be treated as a whole, and relied on T.T.G. Industries on the permanency test. The taxpayer relied on the Supreme Court's decision in Bharti Airtel Ltd. v. Commissioner of Central Excise, Pune, on telecom towers, and on the High Court's own earlier ruling for Sterling and Wilson on solar power plants.
Held / Ruling
Relying on the appellate authority's own findings, the High Court noted that tower sections, nacelle and blades are bolted together at site and the WTG can be de-erected and re-erected elsewhere without damage; only the foundation is fixed. Applying the six tests summarised in Bharti Airtel (nature and object of annexation, intention of the parties, functionality, permanency and marketability), the Court found that the WTG is attached for its own better functioning, not for the enjoyment of the foundation, and can be dismantled, relocated or sold. The WTG was held to be movable property amounting to goods, so the contracts were a composite supply and not works contracts. The assessment, penalty and appellate orders were set aside and the matter remanded for fresh assessment. The Supreme Court found no ground to interfere and dismissed the Revenue's SLPs.
Key takeaways for taxpayers
- Attachment to the earth does not by itself make plant immovable; the Bharti Airtel six-test framework now applies to renewable energy equipment.
- Where equipment arrives in parts, is bolted together at site and can be dismantled without damage, the end product is likely goods, which takes the contract outside Section 2(119).
- WTG suppliers facing 18% works contract demands for July 2017 to March 2019 can rely on this ruling, as the SLP has been dismissed.